⚡Bullet Train Project Update: 343 KM Viaduct, 5 KM of Key Tunnel Excavation Completed

By ANI

Get latest articles and stories on Business at LatestLY. Providing a progress update as of March 29, 2026, NHSRCL said that key structural works along the corridor have advanced significantly. "Out of 508 km, 343 km viaduct and 434 km pier work has been completed," the corporation said. The update also noted that several bridge works along the route have been finished. "17 river bridges, 05 PSC (pre-stressed concrete) and 13 steel bridges completed," NHSRCL said.

...