Get latest articles and stories on Latest News at LatestLY. PSU major NHPC Ltd on Saturday said the 2,000 MW Subansiri hydropower project, which was stalled for nearly eight years due to intense protests by many groups in Assam, will be commissioned by March 2022.

Guwahati, Dec 5 (PTI) PSU major NHPC Ltd on Saturday said the 2,000 MW Subansiri hydropower project, which was stalled for nearly eight years due to intense protests by many groups in Assam, will be commissioned by March 2022.

Union power ministry's secretary Sanjiv Nandan Sahai, Arunachal Pradesh chief secretary Naresh Kumar and the company's chairman and managing director A K Singh visited the Subansiri Lower Hydro Electric project sites on Friday and inaugurated the restart of the power-house works, NHPC said in a statement.

Also Read | Farmers' Protests: Indian Railways Diverts, Short Terminates Trains in Punjab Again.

"Later in the day, the power secretary held a review meeting wherein NHPC chief briefed about the various construction activities and downstream river protection works undertaken by the company. It was assured that the project shall be commissioned by March 2022," it added.

Construction work of the ambitious project at Gerukamukh along the Assam-Arunachal Pradesh border on Subansiri river was halted from December 2011 to October 2019 due to protests by locals and many groups fearing about safety and the adverse impact on the downstream of the river.

Also Read | Moto G9 Power Smartphone to Be Launched in India on December 8; Expected Prices, Features & Specifications.

According to a company estimate in January 2020, the cost of the mega project, which was scheduled to be commissioned in December 2012, had escalated to around Rs 20,000 crore.

The initial project cost was estimated at Rs 6,285 crore.

The Centre had allocated a total of Rs 11,000 crore as of December 2010 for construction of the dam.

Multiple committees were formed by the Assam government and the Centre to address the concern of the agitators. The outcomes of their reports varied from one to another.

(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)