Jiribam-Imphal, Manipur Project Progress Report:
1) 89.20% of work completed
2) Tunnels- 48 of 52 completed
3) Stations: 6 of 11 constructed
4) Bridges:
- Major: 11; substructure of 7
and superstructure of 5 completed
- Minor: 101 of 129 completed
~@RailMinIndia pic.twitter.com/AXCjU82gdh— Prasar Bharati News Services & Digital Platform (@PBNS_India) August 20, 2022
(SocialLY brings you all the latest breaking news, fact checks and information from social media world, including Twitter (X), Instagram and Youtube. The above post contains publicly available embedded media, directly from the user's social media account and the views appearing in the social media post do not reflect the opinions of LatestLY.)