Latest News | IRB Infrastructure Trust Wins Rs 1,720 Cr Arbitration Award

Get latest articles and stories on Latest News at LatestLY. Yedeshi Aurangabad Tollway Ltd (YATL), a special purpose vehicle of IRB Infrastructure Trust, has won an arbitration award of Rs 1,720 crore for a highway project, a statement said on Sunday.

New Delhi, Jan 28 (PTI) Yedeshi Aurangabad Tollway Ltd (YATL), a special purpose vehicle of IRB Infrastructure Trust, has won an arbitration award of Rs 1,720 crore for a highway project, a statement said on Sunday.

The YATL had initiated arbitration proceedings against the National Highways Authority of India (NHAI) after the authority disputed the company's claim for the extension of the concession period by 870 days and compensation of Rs 1,751 crore, the statement said.

Also Read | Union Budget 2024-25: What is an Interim Budget? How is It Different From a Regular Budget? All You Need to Know.

IRB Infrastructure Developers Ltd is the sponsor of IRB Infrastructure Trust. IRB was the EPC contractor for YATL and continues to be the project manager for YATL.

The arbitration was based on the compensation payable to the IRB towards time and cost overrun suffered during the construction period on account of delays attributable to the NHAI and certain Force Majeure events, it added.

Also Read | Union Budget 2024-25 Expectations For Salaried Taxpayers: From Simplification of Capital Gains to Increase in Section 80C Deduction Limit, Here's What To Expect From Interim Budget.

After thoroughly hearing both sides, the statement said the Arbitration Tribunal has directed NHAI to pay compensation of Rs 1,720 crore including Interest payable as on date of award.

The Arbitration Tribunal has directed NHAI to grant extension of 689 days to the concession period, the statement added.

IRB incorporated YATL for implementation of Yedeshi Aurangabad NH211 BOT highway project and executed the concession agreement in May 2014.

YATL commenced construction of the project from July 1, 2015, and it was scheduled to be completed within 910 days i.e. December 26, 2017. However, due to delay in handing over of land and for other reasons attributable to NHAI, the project completion on entire project length was delayed and the project was finally completed on September 24, 2020, the statement said.

As a result of above delay, YATL incurred time and cost overrun for which it claimed compensation from NHAI on March 12, 2021. The same was disputed by NHAI and led to arbitration.

(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)