India News | CAG Criticises Army Ordnance Corps for Delays in Placing Procurement Orders, Extra Expenditure
Get latest articles and stories on India at LatestLY. The Comptroller and Auditor General (CAG) on Monday criticised the Army Ordnance Corps (AOC) for instances of delays in placing procurement orders and extra expenditure.
New Delhi, Jul 18 (PTI) The Comptroller and Auditor General (CAG) on Monday criticised the Army Ordnance Corps (AOC) for instances of delays in placing procurement orders and extra expenditure.
In a press release, the CAG said delays in placing orders and materialisation of supplies in case of critical items was an "inherent" problem affecting operational preparedness of the Army.
"Against the prescribed time frame of 23 weeks in Defence Procurement Manual, delay of 13 to 301 weeks was noticed in certain supply orders. The delays were mainly in obtaining acceptance of necessity and completing the tendering process within the bid validity period," the CAG said.
"Against the supply orders/indents placed on Ordnance Factories, Defence Public Sector Undertakings and other vendors, supply orders valuing more than Rs 700 crore were outstanding beyond the delivery period and awaiting completion for the last one to 19 years," it said.
Also Read | Kerala Shocker: Female NEET Candidate Asked To Remove Underwear During Medical Entrance Examination.
The report was tabled in Lok Sabha on Monday.
The AOC is responsible for providing material and logistics support to the Indian Army during war and peace.
The inventory management functions of AOC primarily involve provisioning, receipt, storage, preservation, accounting, stocktaking and issue of ordnance stores.
The CAG also cited cases of "extra expenditure" due to failure to accept the tender within prescribed period and procurement at higher rates.
"Failure to accept the tender within the validity period in one case led to retendering and consequent placement of supply orders at an extra expenditure of Rs 6.75 crore," the CAG said.
"There were instances of rates in central procurements at central depots being higher than their local purchases rates made within the last one to six months resulting in an extra expenditure of Rs 4.36 crore," it said.
The CAG said procurement agencies did not utilise the provision of repeat order/option clause and instead placed fresh supply orders at rates higher than the earlier ones, resulting in an extra expenditure of Rs 3.89 crore.
(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)