Latest News | SJVN's 1,320-MW Buxar Thermal Power Plant Enters Advanced Construction Phase
Get latest articles and stories on Latest News at LatestLY. State-owned SJVN Ltd on Monday said its 1,320-MW Buxar Thermal Power Plant has entered the advanced construction phase.
New Delhi, Jan 17 (PTI) State-owned SJVN Ltd on Monday said its 1,320-MW Buxar Thermal Power Plant has entered the advanced construction phase.
"SJVN's 1,320-MW Buxar Thermal Power Project in Bihar achieved another milestone today (on Monday) with Jacking up of ceiling girder (1,400 tonnes) for first boiler unit," SJVN said in a statement.
The activity was virtually activated by SJVN Chairman and Managing Director Nand Lal Sharma from the company's corporate headquarters at Shimla.
Sharma said that with this jacking-up activity, the project's first boiler unit will start taking its shape.
Also Read | India Records 2,58,089 New COVID-19 Cases, 385 Deaths; Positivity Rate at 19.65%.
He added that the entire process will be completed in four stages and in each stage ceiling girder will jack up and jack down to add pressure parts and other components in the boiler assembly.
Sharma reiterated the commitment to complete the project as per schedule i.e June 2023 for the first unit and January 2024 for the second unit.
He further informed that a capital expenditure of Rs 4,617.45 crore has already been incurred on the project.
During the year 2021-22, a capital expenditure of Rs 2,619.06 crore has been incurred till date. The project is being constructed at an estimated cost of Rs 10,439.09 crore. HRS hrs
(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)