.@RailMinIndia informs that as on March 16 the overall progress of the Bhairabi - Sairang railway line (51.38 km) project of Mizoram is 87%.
Bridge Works Completed
🔹Major: 5/55
🔹Minor: 75/87
🔹ROB/RUB: 6/9
🔹Tunnels: 12600m/12853m pic.twitter.com/2zV0zcUf0g— Prasar Bharati News Services & Digital Platform (@PBNS_India) March 23, 2023
(SocialLY brings you all the latest breaking news, fact checks and information from social media world, including Twitter (X), Instagram and Youtube. The above post contains publicly available embedded media, directly from the user's social media account and the views appearing in the social media post do not reflect the opinions of LatestLY.)