New Delhi, Jun 9 (PTI) As many as 448 infrastructure projects, each entailing an investment of Rs 150 crore or above, were hit by a cost overrun of more than Rs 5.55 lakh crore in April 2024, according to an official report.

According to the Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,838 projects, 448 reported cost overruns and 792 projects were delayed.

Also Read | Congress Passes Resolution to Make Rahul Gandhi Leader Of Opposition in Lok Sabha: What is LoP? What Are the Privileges Associated With the Post? All You Need to Know.

The total original cost of implementation of the 1,838 projects was Rs 27,64,246.50 crore, and their anticipated completion cost is likely to be Rs 33,19,601.84 crore, which reflects an overall cost overrun of over Rs 5,55,355.34 (20.09 per cent of original cost), the ministry's latest report for April 2024 showed.

According to the report, the expenditure incurred on these projects till April 2024 is Rs 1,692,997.5 crore crore, which is 51 per cent of the anticipated cost of the projects.

Also Read | NDA Government Formation 2024: Who Wants Which Ministry? Check Likely List of New Cabinet Ministers.

However, the number of delayed projects decreased to 514 if the delay is calculated on the basis of the latest schedule of completion, it added.

Of the 792 delayed projects, 220 have overall delays in the range of 1-12 months, 192 have been delayed for 13-24 months, 259 projects for 25-60 months, and 121 projects for more than 60 months.

The average time overrun in these 792 delayed projects is 35.4 months.

Reasons for time overrun, as reported by various project implementing agencies, include land acquisition, environmental clearance, financial issues, contractual/internal issues, manpower shortage and litigation issues.

(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)