Kolkata, Jun 23 (PTI) Around 4.66 lakh homes scheduled for delivery in 2020 may miss the deadline as most of the states had allowed six months extension to complete the projects in the wake of the COVID-19 pandemic, a global property consultant said on Tuesday.
The National Capital Region, Mumbai and Bengaluru had completion of more than one lakh units each lined up in 2020, while Pune had 68,800, Kolkata 33,850, and Hyderabad nearly 30,500 units. Chennai had the least pending delivery of 24,650 units for this year.
Also Read | Oppo Reno 3 A With Snapdragon 665 Chipset Launched; Check Prices, Features, Variants & Specifications.
"Homebuyers will have to adjust to new realities. As many as 4.66 lakh units were slated to be delivered in 2020. With almost zero construction activity in the last few months due to the lockdown, completion deadlines for almost all these projects have been extended," ANAROCK Property Consultants chairman Anuj Puri said.
Most state housing regulators (RERA) have given a six-month extension to developers on previously committed timelines following demands for it.
"The government must intervene to address multiple challenges including labour shortage in top cities," Puri said.
Even if developers have the financial strength, it will still take a while for most of them to resume construction because lakhs of labourers have left cities and returned to their villages, he said.
"Moreover, many of the top cities are still grappling with the virus," Puri said.
In 2021, another 4.12 lakh units are lined up for delivery in top cities of the country. Kolkata had nearly 59,000 units meant to be delivered in two years 33,900 units in 2020 and nearly 25,100 units in 2021.
(The above story is verified and authored by Press Trust of India (PTI) staff. PTI, India’s premier news agency, employs more than 400 journalists and 500 stringers to cover almost every district and small town in India.. The views appearing in the above post do not reflect the opinions of LatestLY)