Bullet Train Progress (as on 13.12.22) shared by @RailMinIndia
Physical Progress (as on 30.11.22)- 24.10%
Gujarat: 29.78%
Maharashtra: 13.26%
Completed work in Gujarat:
-Number of Piles– 28,293
-Pier work- 118km
-15.7 km Girders launched pic.twitter.com/bZIZtgk0pN— Prasar Bharati News Services & Digital Platform (@PBNS_India) December 19, 2022
(SocialLY brings you all the latest breaking news, fact checks and information from social media world, including Twitter (X), Instagram and Youtube. The above post contains publicly available embedded media, directly from the user's social media account and the views appearing in the social media post do not reflect the opinions of LatestLY.)