Kolkata, Jul 12 (PTI) State-run West Bengal Power Development Corporation Ltd (WBPDCL) has started preliminary works for setting up its Rs 4,400 crore Sagardighi super- critical plant from this month and expects to complete the construction of the unit over the next three-and-half years, an official said on Sunday.

The company has decided to consider July 1 as the "zero date" for the implementation of the 660-MW thermal power plant project in Murshidabad district, he said.

Also Read | Xiaomi Redmi Note 8 India Prices Hiked; Becomes Expensive By Rs 500.

"Preliminary works like ground-levelling have commenced. July 1 is the zero date for the Sagardighi super- critical power plant project.

"It will take 42 months to complete the construction of the unit and another three months will be required for synchronisation before the commission of it," WBPDCL director Indranil Dutta told PTI.

Also Read | 2020 Honda City To Be Launched in India on July 15; Price in India, Features, Variants & Specifications.

Usually, the project completion period is counted from the zero date.

The total project cost was estimated at Rs 4,400 crore, he said.

"The financial closure has been achieved and the Power Finance Corporation is offering the debt," he said.

Bharat Heavy Electricals Ltd (BHEL) has bagged an order worth Rs 3,500 crore for supplying boiler, turbine, generator (BTG) for the project, he said.

The WBPDCL has four units of 1600-MW in Sagardighi and the fifth one will increase the plant's capacity to 2,260 MW.

The power producer has four more plants in Bandel, Bakreswar, Kolaghat and Santaldihi and an overall generation capacity of 3,150 MW. PTI